Client: Swee Hong Engineering Construction Pte Ltd

 

  • Project Title: T2136 - Sewer diversion at Springleaf Station

  • Work: Jet Grouting Work

  • Date Commenced Jan 2014

  • Date Completed Jan 2014

  • Project Sum $79,565.00

 

Client: Ume Construction Pte Ltd

 

  • Project Title: Proposed new erection of a 3 storeys detached dwelling house with basement on lot 98814A mk 27 at 17 Jalan Haji Salam, Singapore

  • Work: Soldier Piling, Steel Plate & Raker Strutting Work

  • Date Commenced Sept 2013

  • Date Completed March 2014

  • Project Sum $57,159.00

 

Client: YCM Consultancy & Construction Pte Ltd

 

  • Project Title: Proposed new erection of a 2 storey semi-detached dwelling house with an attic on Lot 00425M 24 ts on 35 One Tree Singapore

  • Work: Sheet Piling and Strutting Work

  • Date Commenced Nov 2013

  • Date Completed Jan 2014

  • Project Sum $110,000.00

 

Client: BSI (1990) Pte Ltd

 

  • Project Title: Proposed erection of a 5 storey with attic party wall development comprising of residential flats (total 36 units) with swimming pool, gym & mechanized carpark on lot 99289K MK24 at 524, 526, 528, 530 Upper Serangoon Road (serangoon planning area). - Presto

  • Work: Sheeting Piling, Strutting, King post and Temporary Decking work

  • Date Commenced May 2013

  • Date Completed Dec 2014

  • Project Sum $981,503.44

 

Client: Singapore Piling and Civil Engineering Pte Ltd

 

  • Project Title: Proposed new erection of a mixed used development comprising of a 17 storey business park, a 2 storey rentail blk, a 5 storey office blk and a 2 basement carpark at fusionopolis phase 5 plot 1,2,3 on lots 5012w, 5013v & 5019x mk3 at fusionpolis place

  • Work: Strutting, Ground anchor, Soil Nail, Sheet Piling And Temorary Decking

  • Date Commenced April 2013

  • Date Completed Aug 2014

  • Project Sum $1,650,000.00

 

Client: BSI (1990) Pte Ltd

 

  • Project Title: Proposed erection of a single user 10 storeys warhouse development with commerical uses on lot 03584L mk 11 at  Sungei Kadut Drive

  • Work: Sheeting Piling and Strutting

  • Date Commenced Sept 2013

  • Date Completed Jan 2014

  • Project Sum $280,000.00

 

Client: Interpro Construction Pte Ltd

 

  • Project Title: Proposed strata landed housing development comprising 8 units of 3 storey terrace housing development comprising 8 units of 3 storey terrace houses with a basement carpark on lots 00742l (pt) & 95043c (pt) mk 26 at  East Coast Drive (Bedok planning area)

  • Work: Sheet Piling, Soldier Piling & Strutting Works

  • Date Commenced June 2013

  • Date Completed  July 2014

  • Project Sum $582,890.00

 

Client: GS Engineering And Construction

 

  • Project Title: Proposed Erection of a 16 storey regional hospital, 9 storey community hospital and 8 storey specialist's outpatient clinics with 2 basement carparks and ancillary services at Jurong East Street 21/ Boon Lay Way / Toh Guan Road on mk 05 Lot 05564P, 05567k, 05572x, 08275p, 08386x, Singapore

  • Work: Soldier PIling, Sheet Piling, King Post And Strutting Work

  • Date Commenced April 2013

  • Date Completed Dec 2014

  • Project Sum $3,578,103.32


Client: BSI (1990) Pte Ltd

 

  • ​Project Title: Asahi Project at 47 Pandan Road (AC15)

  • Work: Soldier Piling, Steel Plate And Strutting Work

  • Date Commenced May 2014

  • Date Completed July 2014

  • Project Sum $20,000.00

 

Client: Lim Wen Heng Construction Pte Ltd

 

  • ​Project Title: Supply & Installation of soldier pile at No.53 Ansen Road

  • Work: Supply & Installation of soldier pile

  • Date Commenced April 2014

  • Date Completed April 2014

  • Project Sum $12,080.40

 

Client: Resource Piling Pte Ltd

 

  • Project Title: Proposed development of an integrated regional hospital, a community hospital and specialist outpatient clinics on Lot 02466A MK21 at Sengkang East Way / Sengkang East Road / Anchorvale - Capping Beam at Mockup Area

  • Work: Supply and installation of sheet piling works.

  • Date Commenced Aug 2014

  • Date Completed Aug 2014

  • Project Sum $70,374.00

 

Client: CES Engineering & Construction Pte Ltd

 

  • Project Title: Proposed condominium housing development comprising of 24 storey residential block with landscaped deck, 2 storey basement carpark and communal facilities @ Fort Road

  • Work: Sheet piling, strutting, temporary decking and jet grouting work.

  • Date Commenced Oct 2012

  • Date Completed Sep 2014

  • Project Sum $2,800,000.00

 

Client: Ken-Pal (S) Pte Ltd

 

  • Project Title: NUS admin block - lift pit

  • Work: Extraction of soldier pile and steel

  • Date Commenced Dec 2014

  • Date Completed Dec 2014

  • Project Sum $6,000.00

 

Client: Interpro Construction Pte Ltd

 

  • Project Title: Proposed erection of a 8 storey residential flat (total 36 units) with swimming pool, communal facilities and mechanised carparking at lorong 34 geylang

  • Work: Sheeting Piling, Strutting and Jet Grouting work

  • Date Commenced Jan 2013

  • Date Completed April 2014

  • Project Sum $566,096.20

 

Client: Interpro Construction Pte Ltd

 

  • Project Title: Proposed conventional landed housing development comprising 6 units of 3 storey terrace houses, 2 units of 3 storey semi detached houses with basement on lots 00742L (PT) & 95043C (PT) MK 26 at East Coast Terrace

  • Work: Installation of sheet pile and strutting work

  • Date Commenced Feb 2014

  • Date Completed Sep 2014

  • Project Sum $185,000.00

 

Client: BSI (1990) Pte Ltd

  • Project Title: Yeo Hiap Seng @ 3 Senoko Way - Shoring for Lift Shaft

  • Work: Installation of  Soldier Piling, Steel plate and strutting work

  • Date Commenced June 2014

  • Date Completed Aug 2014

  • Project Sum: $23,421,60

 

Client: Lim Wen Heng Construction Pte Ltd

 

  • Project Title: Proposed erection of 4 blocks of 5 storey flats with attic (total 171 units) and 2 shops units, one level of basement car parks and with provision for a swimming pool on lot 05596L MK 24 at Lew Lian Vale (Serangoon Planning Area)

  • Work: Supply, installation and dismantling of strutting works

  • Date Commenced July 2014

  • Date Completed Sep 2014

  • Project Sum $89,595.41

 

Client: Ohin Construction Co. Pte Ltd

 

  • Project Title: Jet Grouting Works for MH AR-05 along KPE near Tampines Road (Mugliston Project)

  • Work: Jet grouting work

  • Date Commenced Nov 2014

  • Date Completed Nov 2014

  • Project Sum $36,000.00

 

Client: CHH Construction System Pte Ltd

 

  • Project Title: Proposed new erection of a 2 storey detached single dwelling house with a basement and an attic on mk 26 lot 94516w at 22 La Sale Street, Singapore 456938 (Bedok planning area)

  • Work: Sheet Piling & Strutting Work

  • Date Commenced April 2013

  • Date Completed March 2014

  • Project Sum $400,000.00

 

Client: Sembawang Engineering & Const. Pte Ltd

 

  • Project Title: Proposed Construction of a 60 MGD waterworks and ancillary facilities at Lower Seletar, Singapore

  • Work: Sheet Piling And Strutting work

  • Date Commenced Aug 2011

  • Date Completed May 2014

  • Project Sum: $4,092,686.72

 

 

 

 

 

 

 

 

 

 